Six railroads will install new grade crossing protection equipment at 12 crossing as a result of recent action by the Public Utilities Commission of Ohio.

Norfolk Southern will install lights and gates at the Township Road 212 grade crossing in Arcadia by July 30, 2020.

CSX will install lights and gates as well as remove a spur track at the Main Street crossing in the New Bloomington

The Wheeling & Lake Erie will install light, gates and a new crossing surface at the County Road 504 crossing in Creston, as well as install lights and gates, and complete surface reconstruction at the Center Street crossing in New Washington;

The Kanawha River Railroad will install lights and gates at the Carpenter Road/County Road 13 crossing in Albany.

The Columbus &; and Ohio River Railroad will upgrade lights and gates at the Thornwood Drive crossing in Heath and at the Parrot Street crossing in Mt. Vernon. The crossing surface at Parrot Street also will require traffic signal preemption installed and the crossing surface to be reconstructed.

The CSX, W&LE, KRR and C&OR projects are all to be completed by April 30, 2020.

The Akron Barberton Cluster Railway will install LED lights at the Oak Street crossing in Ravenna, as well as at the Tuscarawas Avenue, Fourth Street, Hopocan Avenue, Cleveland-Massillon Road crossings in the city of Barberton.

Those projects are to be completed by July 31, 2020.

Tags: , , , , , , , ,

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.


%d bloggers like this: