Water Problem Sidelines New Venture Cars

June 4, 2021

An issue with the water supplies in the restrooms has delayed use by Amtrak of new Siemens Venture passenger cars in corridor service in the Midwest and California.

The problem was found during routine testing last November, a California Department of Transportation official said.

A Siemens spokeswoman said the company has found a solution to the problem but further testing is needed before the cars can be delivered.

The spokeswoman said the fix will enable the cars to meet water-quality standards of the Food and Drug Administration and Environmental Protection Agency.

Caltrans is the lead agency overseeing the $386 million, 137-car order for single-level cars that was awarded to Siemens in 2017.

California will receive 49 of those cars while Midwest corridor trains will use 88 cars.

Contractor Sumitomo Corporation has been paid $28 million for its work on the cars, but the Caltrans spokesman said Sumitomo won’t be paid for the cars themselves until the water issue has been resolved.

California officials had hoped to put the cars into revenue service this fall but now the timeline for their debut is unclear.

Four Venture cars have already been delivered to Amtrak in Chicago for testing on the Chicago-Detroit corridor and on the Chicago-Carbondale, Illinois, corridor.

The cars are based on the design Siemens used to build passenger cars for Florida’s Brightline intercity rail passenger service where they began revenue service in December 2017.

Siemens Cars to Replace Sharyo Cars

September 5, 2017

Single-level passenger cars built by Siemens will replace bi-level coaches that were to have been built by Nippon Sharyo. The cars are to be used on Amtrak corridor routes funded by state governments.

The departments of transportation of California and some Midwest states had ordered 130 bi-level cars from Sharyo that were to be built in Rochelle, Illinois.

However, design problems and the inability of a prototype to pass federal rigidity tests delayed the order.

The California Department of Transportation, which is leading procurement of the cars, has said it will substitute 130 Siemens cars for the Sharyo order.

The number of seats will be reduced, but state officials said the time frame for delivering the cars will be shortened from five years to 24 to 34 months.

In the Midwest, the Siemens cars are expected to replace Horizon equipment.